How Often Are lockout/tagout Training and Periodic Inspections Required?

Under 29 CFR 1910.147(c)(6), the employer must inspect each energy control procedure at least annually and certify the inspection. The standard sets no fixed annual retraining interval; instead, retraining is required when job assignments, machines, processes or procedures change, and when an inspection or other evidence shows gaps in an employee's knowledge or use of the procedure.

Updated November 16, 2026 · 29 CFR 1910.147(c)(6) and (c)(7)

Photo illustration for the guide: Lockout/Tagout Training and Periodic Inspection: How Often and What to Document

OSHA's control of hazardous energy standard, 29 CFR 1910.147, sets two recurring duties. First, the employer must conduct a periodic inspection of each energy control procedure at least annually. Second, the employer must train employees before they work under the program and retrain them when specific changes or problems occur. The standard does not set a calendar interval for retraining. It is driven by events, and the annual inspection is one of the main ways those events are found.

Who Needs Lockout/Tagout Training

Paragraph 1910.147(c)(7)(i) says training must make sure employees understand the purpose and function of the energy control program and acquire the knowledge and skills to apply, use and remove energy controls safely. The content depends on the employee's role, as defined in paragraph (b):

RoleWho it isRequired training
Authorized employeeA person who locks out or tags out machines or equipment to perform servicing or maintenanceRecognizing applicable hazardous energy sources, the type and magnitude of energy available in the workplace, and the methods and means needed for energy isolation and control
Affected employeeAn employee who operates or uses a machine being serviced under lockout or tagout, or who works in the area where that servicing happensThe purpose and use of the energy control procedure
Other employeesAnyone whose work operations are or may be in an area where energy control procedures may be usedThe procedure, and the prohibition on attempting to restart or reenergize machines that are locked out or tagged out

An affected employee becomes an authorized employee when their duties come to include servicing or maintenance covered by the standard. At that point they need the authorized employee training. Paragraph (c)(8) also says lockout or tagout may be performed only by the authorized employees who are performing the servicing or maintenance.

Extra Training Where Tags Are Used

When tagout systems are used, paragraph (c)(7)(ii) requires training on the limitations of tags. Employees must learn that:

Advertisement

When Retraining Is Required

Paragraph 1910.147(c)(7)(iii) lists the triggers. Retraining must be provided for all authorized and affected employees whenever there is:

Additional retraining is also required whenever a periodic inspection reveals, or the employer has reason to believe, that there are deviations from or inadequacies in an employee's knowledge or use of the energy control procedures. Retraining must reestablish employee proficiency and introduce new or revised control methods and procedures as needed.

Many employers choose to refresh LOTO training on a fixed schedule as well, but that is a company policy choice. The federal text ties retraining to the events above. Providers who can deliver or update this training are listed in our safety training and consulting directory and the OSHA training finder.

Periodic Inspection: At Least Annually

Paragraph 1910.147(c)(6)(i) requires the employer to conduct a periodic inspection of the energy control procedure at least annually to make sure the procedure and the standard's requirements are being followed. The standard sets these conditions:

Because the inspection is of the energy control procedure, plan it procedure by procedure. Each documented procedure in your program needs its own inspection at least once a year.

What to Certify and Document

The standard requires two separate certifications.

CertificationRequired contentsRule
Periodic inspectionThe machine or equipment on which the procedure was used, the date of the inspection, the employees included, and the person performing the inspection1910.147(c)(6)(ii)
TrainingEach employee's name and dates of training; the employer certifies training has been accomplished and is being kept up to date1910.147(c)(7)(iv)

A simple log per procedure, with the inspector's name, the date, the equipment and the employees reviewed, covers the inspection certification. A training roster with names and dates covers the training certification. Keep both current, since the training certification must show training is being kept up to date.

Procedures That Need Not Be Written Down

Paragraph (c)(4)(i) requires energy control procedures to be developed, documented and used. A note to that paragraph exempts documenting a procedure for a particular machine only when all of these apply: no potential for stored or residual energy or its reaccumulation after shutdown; a single energy source that can be readily identified and isolated; isolating and locking out that source completely deenergizes the machine; the machine is isolated and locked out during servicing; a single lockout device achieves a locked-out condition; the device is under the exclusive control of the authorized employee; the work does not create hazards for other employees; and the employer has had no accidents involving unexpected activation or reenergization of that machine during servicing. The exception covers documentation only, not training.

Group Lockout and Testing

When a crew, craft or department does the servicing, paragraph (f)(3) requires a group procedure that gives each employee protection equivalent to a personal lockout or tagout device, with primary responsibility vested in an authorized employee for a set number of workers. Paragraph (f)(1) sets the sequence to follow when lockout or tagout devices must be temporarily removed to test or position a machine. Both belong in training for the employees who use them.

Annual LOTO Checklist

General information, not legal advice. Rules change and State Plan states may differ, so confirm with the current standard or your state agency.

Sources

Find Providers Near You

Listings: © OpenStreetMap contributors (ODbL), Overture Maps Foundation (CDLA Permissive 2.0), CMS NPI registry, state agencies · Data last updated November 6, 2026 · Sources & method